i-80 Gold Reports Second Quarter 2026 Results; On Track to Achieve Full-Year Guidance as Granite Creek Ramps Up and Development Plan Advances

PR Newswire
Today at 10:16pm UTC

i-80 Gold Reports Second Quarter 2026 Results; On Track to Achieve Full-Year Guidance as Granite Creek Ramps Up and Development Plan Advances

PR Newswire

TORONTO, Aug. 10, 2026 /PRNewswire/ -- i-80 GOLD CORP. (NYSE:IAUX) (TSX:IAU) ("i-80 Gold" or the "Company") reports its financial and operating results, as well as development highlights, for the three and six months ended June 30, 2026.

i-80 Gold Corp. logo

"We delivered another solid quarter, with increased production from Granite Creek as the project continued to ramp up on plan, the advancement of Archimedes on schedule toward becoming our second underground mine, and the start of demolition at the Lone Tree Plant," stated Richard Young, President & CEO. "Additionally, Archimedes drilling results released during the quarter demonstrated the vast exploration potential and the ability to extend its mine life. Our success year-to-date demonstrates the Company's ability to advance multiple projects concurrently. We remain on track to commence gold mining at Archimedes and major construction at Lone Tree in the fourth quarter of this year, marking two important milestones by year-end as we execute our development plan to build a Nevada-focused mid-tier gold producer."

SECOND QUARTER HIGHLIGHTS
Three months ended June 30, 2026 compared to three months ended June 30, 2025.
Unless otherwise stated, all amounts referred to herein are in U.S. dollars.

Development

  • Granite Creek underground development continued ahead of plan increasing access to high-grade headings supporting the ongoing ramp up. The project remains on track to achieve its full-year production guidance, with a published feasibility study anticipated in the third quarter of 2026.

  • Archimedes underground advanced on schedule and largely on budget with the main decline development on track, advancement of the exploration drift, which has since been completed, and commencement of the ventilation raise in preparation for first gold mined by year-end.

  • Lone Tree Plant refurbishment advanced on schedule and on budget as early works and pre-construction readiness activities continued during the quarter, and the commencement of demolition mid-June ahead of major construction. Procurement activities remain on schedule, with approximately 50% of procurement packages, by value, awarded as of mid-July. Project capital remains on budget with minimal contingency drawdown and approximately 40% of capital committed as of mid-July.

  • Completed approximately 19,000 meters of drilling across three projects, including infill drilling at Archimedes underground and Mineral Point open pit in support of planned 2027 technical studies for both projects, as well as resource definition drilling at Granite Creek underground beyond the area covered by the upcoming feasibility study.

  • Permitting largely on track across the development plan as permitting actions continued to advance across the portfolio.

Financial and Operating

  • Revenues were $24.3 million, representing 5,335 ounces in gold sold(2) at an average realized gold price(1) of $4,522 per ounce, compared to $27.8 million represented by 8,400 ounces at an average realized gold price(1) of $3,301 per ounce in the prior year period. The decrease in revenues was primarily driven by lower gold sold at Granite Creek as a result of delays at the third-party processing facility, partially offset by a higher average realized gold price(1). Revenues in the prior year quarter were higher due to the finalization of the third-party toll processing agreement in March 2025 and the processing of a higher volume of stockpile material.

  • Gold production increased to 11,098 ounces from 4,178 ounces in the prior year period. The Company remains on track to achieve its full year production guidance range.

  • Gross profit increased to $8.6 million from $0.8 million in the prior year period due to a higher realized gold price. 
  • Net loss increased to $52.5 million compared to $30.2 million in the prior year period, due primarily to higher pre-development, evaluation and exploration costs incurred as the Company advances multiple projects within its development plan. The higher costs were related to drilling programs at the Ruby Hill property. Upon declaration of mineral reserves, certain pre-development, evaluation and exploration expenditures that are currently expensed will be capitalized.

  • Net loss per share increased to $0.06 compared to a $0.05 loss in the prior year period, primarily due to a higher net loss, partially offset by an increase in the weighted average number of common shares outstanding following the equity financing in May 2025.

  • Adjusted net loss(1) increased to $41.2 million compared to $26.5 million in the prior year period due to increased spending on pre-development, evaluation and exploration expenses, partially offset by higher gross profit.

  • Cash used in operating activities increased to $49.6 million compared to $11.3 million in the prior year period as a result of comparative working capital changes of $20.9 million primarily as a result of increased inventory due to third-party processing availability and higher pre-development, evaluation and exploration expenses which was partially offset by higher gross profit.

  • Cash and cash equivalents were $464.6 million as of June 30, 2026, a decrease of $49.0 million compared to March 31, 2026, primarily due to cash used in operations of $49.6 million, capital expenditures of $21.5 million primarily driven by the start of the Lone Tree Plant refurbishment project partially offset by a release of restricted cash of $16.9 million and proceeds from warrant exercises.

Sustainability

  • Advanced community engagement across Northern Nevada by progressing community development, workforce development, and grant funding initiatives, including a joint $300,000 donation with Franco-Nevada Corporation to support development of the first licensed childcare facility in Eureka County, neighboring the Company's Ruby Hill property.

  • Strengthened Board with the appointment of Stephen Gottesfeld at the annual general meeting, bringing nearly 30 years of global mining experience in environmental, sustainability, legal and governance matters across the mine lifecycle.


UPCOMING CATALYSTS

Over the next 18 months, the Company is targeting the following key catalysts while continuing to identify opportunities to optimize the development schedule:

Archimedes Underground

  • First gold mined — Q4 2026

Lone Tree Plant

  • Commence constructionQ4 2026
  • Completion of detailed engineering — late Q1 2027
  • Filtration plant completion — early Q4 2027
  • First gold pour — Q4 2027

Technical Studies

  • Granite Creek underground (Feasibility) — Q3 2026
  • Cove underground (Feasibility) — Q3 2026
  • Archimedes Underground (Feasibility) — approximately mid-2027
  • Mineral Point Open Pit) (Pre-Feasibility) — approximately mid-2027
  • Granite Creek open pit (Pre-Feasibility) — timing under review


OUTLOOK

The Company remains on track to meet its 2026 guidance as originally published in its 2025 Year End Annual Report on Form 10-K on February 19, 2026 subject to the following:
Growth capital expenditures are expected to be largely in line with the $150 million to $175 million guidance.

  • Lone Tree plant refurbishment capital expenditures are expected to be lower in 2026 than guided, management was conservative in estimating expenditures for Lone Tree during the recapitalization planning process earlier in year to ensure that the Company raised sufficient capital.
  • Archimedes expenditures are expected to be higher reflecting a change in strategy for long-term surface infrastructure. Based on positive drill results, management is pivoting from refurbishment of certain existing facilities on site to construction of a new worker change facility and additional offices that are expected to improve operating effectiveness both for Archimedes and Mineral Point.
  • Exploration expenses are expected to be approximately $10 million lower in 2026 due to the personnel shortages at the Archimedes project and drill rig availability as well as contractor personnel shortages at Mineral Point project.

This outlook, including expected results and targets, is subject to various risks, uncertainties and assumptions, which may impact future performance and the Company's ability to achieve the results and targets discussed in this section. Please refer to "Forward-Looking Information" section. The Company may, but is under no obligation to, update this outlook depending on changes in metal prices and other factors.

SUMMARY OF FINANCIAL AND OPERATING RESULTS



Three months ended

June 30,

Six months ended

June 30,



2026

2025

2026

2025

Revenue

$000s

24,348

27,836

76,738

41,884

Gross profit

$000s

8,618

798

24,697

3,704

Net loss

$000s

(52,527)

(30,215)

(131,128)

(71,420)

Net loss per share

$/share

(0.06)

(0.05)

(0.15)

(0.14)

Adjusted net loss

$000s

(41,164)

(26,509)

(69,889)

(50,105)

Adjusted net loss per share1

$/share

(0.05)

(0.04)

(0.08)

(0.10)

Cash used in operating activities

$000s

(49,584)

(11,335)

(94,664)

(34,036)

Cash and cash equivalents

$000s

464,555

133,691

464,555

133,691

Gold produced

oz

11,098

4,178

21,964

14,326

Gold ounces sold2

oz

5,335

8,400

15,923

13,352

Average realized gold price1

$/oz

4,522

3,301

4,801

3,124

Pre-development, evaluation and exploration expenses

$000s

29,264

9,045

54,962

18,590

Notes to table above:

1This is a Non-GAAP Measure; please see "Non-GAAP and Supplementary Financial Performance Measures" section.



2Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).



Granite Creek Property

The Granite Creek property includes the Granite Creek underground project, a fully permitted, constructed and operating mine, and the Granite Creek open pit oxide deposit adjacent to the underground project. Granite Creek underground is the Company's first brownfield project to be redeveloped and is currently ramping up towards steady-state gold output.

Granite Creek Property


Three months ended
June 30,

Six months ended
June 30,

Operational Statistics


2026

2025

2026

2025

Mining






Oxide mineralized material mined

tonnes

12,039

24,074

23,752

39,397

Sulfide mineralized material mined

tonnes

13,568

11,201

33,282

25,844

Low-grade mineralized material mined

tonnes

9,338

16,173

22,375

39,019

Waste mined

tonnes

37,405

31,947

77,762

59,409

Total material mined

tonnes

72,350

83,395

157,171

163,669







Oxide mineralized material grade

g/t

7.44

11.38

8.14

11.74

Sulfide mineralized material grade

g/t

6.49

7.43

6.29

7.93

Low-grade mineralized material grade

g/t

3.13

3.03

2.97

2.88







Processing






Processed mineralized material - sulfide

tonnes

9,055

7,014

35,460

7,014

Processed mineralized material - heap leach

tonnes

18,750

5,827

52,587

Total processed mineralized material 

tonnes

9,055

25,764

41,287

59,601







Ore purchase agreement (high and low grade oxide)






Oxide mineralized material sold1

tonnes

15,505

16,317

32,681

28,798







Total gold produced

oz

8,634

1,941

17,532

9,392

Total gold sold1

oz

2,052

5,981

10,818

9,086







Underground mine development (pre-development)

meters

360

211

747

365

Drilling

meters

1,211

586

3,135

586







Financial Statistics


2026

2025

2026

2025

Mining cost (total mineralized material and waste)

$/t

178

175

169

173

Processing cost (processed mineralized material)

$/t

325

133

293

74

Site general and administrative ("G&A") (total mineralized material mined)

$/t

57

34

50

32

Operating costs2

$000s

7,106

22,067

37,835

30,386

Royalties2

$000s

517

1,148

3,119

1,654

Sustaining capital expenditures3

$000s

1,672

778

4,268

201

Growth capital expenditures3

$000s

7,234

336

9,445

1,290

Capital expenditures

$000s

8,906

1,114

13,713

1,491

Pre-development, evaluation and exploration expenses

$000s

7,882

5,949

19,278

9,719

Notes to table above:

1Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).

2Operating costs excluding depletion, depreciation, amortization, and royalties. Royalties exclude NSR royalty payments.

3This is a Non-GAAP and Supplementary Financial measure; please see "Non-GAAP and Supplementary Financial Performance Measures" section.

Granite Creek Underground

Mining & Processing

Mineralized material mined at Granite Creek underground is processed as follows: (i) sulfide mineralized material is processed at a third-party processing facility and subject to a toll milling agreement entered into in March 2025, (ii) high-grade and low-grade oxide mineralized material is subject to an ore sales agreement. Low-grade oxide mineralized material was sold under the ore purchase beginning in the first quarter of 2026, and (iii) residual leaching of low-grade oxide material previously placed on a segregated section of the Company's Lone Tree heap leach facility continues with no additional mineralized material being placed after the first quarter of 2026.

During the quarter, mining activities at Granite Creek were impacted by ground conditions in two of the mine highest-grade headings, which temporarily restricted access to high-grade mineralized material and deferred a portion of planned high-grade tonnes during the quarter. Remediation of the affected headings was completed and access was re-established late in the quarter, allowing these areas to contribute to production beginning in the third quarter.

Throughout the quarter, advancement of the main decline as well as horizontal development continued to progress ahead of the mine plan, with year-to-date development footage exceeding plan. As a result, the number of available high grade mineralized material headings has increased significantly throughout the quarter. The Company remains on track to meet its full-year production guidance.

Water inflow volumes to the mine remained largely unchanged and continue to be managed well using the current underground pumping system, which presently operates near capacity. Work on an enhanced pumping system, that includes expanded sumps at lower levels and higher-capacity pumps, advanced during the quarter. Pumps were sized and ordered with installation continuing throughout the remainder of the year to increase overall water discharge capacity as the mine progresses at depth. Further, initial phases of commissioning a second water treatment plant began in late July, with mechanical completion having recently been completed. The second water treatment plant will increase surface water treatment capacity to approximately 3,500 gallons per minute to support the Company's long-term groundwater management objectives.

At June 30, 2026, the Company had in-process material containing over 5,300 recoverable ounces at its third-party processing facility. The Company expects the material to be processed during the third quarter of 2026. Approximately 1,800 ounces of gold was also held in inventory at June 30, 2026. Gold ounces sold were lower than the prior year periods due to availability at the third-party processing facility.

Processing cost per unit has increased compared to the prior year periods due to a higher proportion of sulfide material being processed at the third-party processing facility.

During the three months ended and six months ended June 30, 2026, growth capital expenditures were primarily related to the water treatment plant project. Sustaining capital expenditures were related primarily to the electrical substation replacement.

Pre-development, evaluation, and exploration expenses were $7.9 million for the three months ended June 30, 2026, which were related to underground mine development and infill drilling to upgrade mineral resources and step-out drilling.

Drill Program

During the quarter, the Company continued infill and step-out drilling at Granite Creek. The underground drill program remained focused on infill drilling to support resource conversion and mine planning. Drilling progressed slower than anticipated during the quarter due to water management, maintenance downtime, and rig relocation. The updated mineral resource estimate is near completion and under internal review. The feasibility study is now expected to be completed in the third quarter of 2026.

Granite Creek Open Pit

Preparation for a pre-feasibility trade-off study has commenced following the completion of the Granite Creek open pit preliminary economic assessment, prepared in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and the corresponding Initial Assessment prepared under Subpart 1300 of Regulation S-K ("S-K 1300"), each filed on March 31, 2025 ("PEA"). Simultaneously, technical trade-off analyses are being conducted to optimize project economics. Based on preliminary assessments of potential environmental impacts, the project may require preparation of an Environmental Impact Statement ("EIS") under the Bureau of Land Management ("BLM") process. Early-stage pre-permitting activities and technical studies are currently underway, followed by planned baseline field studies commencing in 2027 to support the National Environmental Policy Act ("NEPA") permitting process.

Ruby Hill Property

The Ruby Hill property includes the Archimedes underground project, the Company's second planned underground mine for which construction began during 2025, and Mineral Point open pit, which is a large oxide gold and silver deposit with the potential to become the Company's largest gold producing asset. 

 Ruby Hill Property


Three months ended
June 30,

Six months ended
June 30,

Operational Statistics


2026

2025

2026

2025

Heap Leach






Gold produced

oz

485

713

878

1,336

Gold sold

oz

690

665

1,073

1,117







Underground mine development (pre-development)

meters

899

1,559

Archimedes drilling

meters

3,124

7,386

Mineral Point drilling

meters

14,836

1,749

15,586

1,749







Financial Statistics


2026

2025

2026

2025

Processing cost (produced oz)

$/oz

3,124

1,640

3,228

1,644

Site G&A (produced oz)

$/oz

658

1,174

755

1,191

Operating costs

$000s

2,639

1,726

3,552

2,808

Royalties1

$000s

92

66

145

103

Sustaining capital expenditures2

$000s

152

719

469

911

Growth capital expenditures2

$000s

2,422

3,170

Capital expenditures

$000s

2,574

719

3,639

911

Pre-development, evaluation and exploration expenses

$000s

20,083

1,898

32,466

5,089

Notes to table above:

1

Royalties excludes Net Smelter Return royalty repayments

2

This is a Non-GAAP and Supplementary Financial measure; please see "Non-GAAP and Supplementary Financial Performance Measures" section.

The Company continues to leach the historic leach pads on the Ruby Hill property, recovering gold. Year-to-date gold production from the historic leach pad remained below expectation as infiltration on the pad remained challenging. Higher processing cost per ounce compared to the prior year periods was due to lower produced ounces. For the residual leaching process, management continues to focus on managing ponding, maximizing the area under leach, and optimizing cyanide application rates.

Archimedes Underground

During the quarter, underground development at the Archimedes project continued to advance on schedule, with 899 meters of development completed during the quarter, supported by favorable ground conditions and high productivity rates from contractors. Pump testing was conducted on a recently completed dewatering well, and permitting activities for below the 5,100-foot level continued to advance as planned. The planned start of mining above the 5,100-foot level is fully supported by existing permits and is not dependent on the timing or outcome of permitting activities below the 5,100-foot level. The Company continues to expect to achieve first gold from Archimedes in the fourth quarter of 2026.

Growth capital expenditures for the three and six months ended June 30, 2026 were primarily related to heavy mobile equipment, infrastructure upgrades, power upgrades and mine load centers for the underground. 

Pre-development, evaluation and exploration expenditures were $20.1 million and $32.5 million for the three and six months ended June 30, 2026. $20.1 million and $32.5 million for the three and six months ended June 30, 2026. Pre-development, evaluation and exploration expenditure were higher than the prior year periods primarily due to underground development at the Archimedes underground project which began in the third quarter of 2025. Development during the quarter focused on completion of the exploration drift to establish drilling platforms to access the ongoing definition drilling program for the Ruby Deeps zones at depth. Further development included commencement of the first ventilation raise.

Drilling activities during the quarter included the completion of the 2025-2026 program in the upper 426 zone and commencement of the 2026 infill drill program with 3,124 meters of infill drilling completed in the lower 426 and Ruby Deeps zones in support of a feasibility study. The latest assay results from the 2025-2026 drill program were published during the second quarter in a press release dated June 25, 2026. The results continued to confirm high-grade mineralization, demonstrate continuity within the planned mining areas, and extend mineralization beyond the boundaries of the current mineral resource estimate supporting the 2025 PEA. Drilling also continued to intersect significant intervals of oxide mineralization not included in the current mineral resource estimate.

An infill drilling program largely within the lower portion of the 426 zone and Ruby Deeps zone commenced in the second quarter of 2026, targeting approximately 55,000 meters planned across 140 drill holes in support of the planned Archimedes Feasibility Study. The drill program is encountering slower than planned progress due to contractor staffing availability. As a result, the Archimedes feasibility study is now anticipated to be completed approximately mid-year 2027.

Mineral Point Open Pit

At Mineral Point open pit, the Company advanced its surface drill program during the quarter as part of the largest 12-month drill program in the Company's history, completing approximately 14,836 meters of core drilling and reverse circulation drilling with a fleet of up to five drill rigs, primarily for infill drilling of the currently classified inferred resources. The drill program encountered slower than planned progress due to drill rig and contractor staffing availability, as well as slower penetration rates than expected in the sanded dolomite unit. Management expects to increase the overall drilling rate for the remainder of the year with mobilization of additional rigs, however, completion of the drill program is now expected in the first quarter of 2027. The results from this program will support a pre-feasibility study, which is expected at approximately mid-year 2027, pending timing of the drilling program. Early-stage pre-permitting activities continued to progress during the quarter.

Cove Underground

Cove is an advanced stage exploration project and is expected to be the Company's third underground mine. During the second quarter,  the Company continued to advance technical and economic studies for the Cove Underground project. Various baseline studies and agency comment responses were submitted to the BLM. In addition, water pollution control permit renewal and modification applications were submitted to NDEP—BMRR for the underground mine and rapid infiltration basins. Additional federal and state permitting actions continue to progress.  A feasibility study for Cove is expected to be completed in the third quarter of 2026.

Lone Tree Plant Refurbishment

The Lone Tree Plant (the "Plant") is currently undergoing refurbishment following a positive construction decision in the first quarter of 2026. i-80 Gold is one of two gold companies in Nevada with an autoclave processing plant (the other being owned by Nevada Gold Mines Inc., a joint venture between Barrick Mining Corporation and Newmont Corporation).

The Plant is envisioned to process material from the Company's three underground mines, Granite Creek, Archimedes, and in the future Cove, to establish a regional hub-and-spoke mining and processing model. Upon refurbishment and commissioning, the Plant will allow the Company to transition from toll milling to owner-operated processing. This shift is expected to materially increase operating margins and enhance free cash flow generation.

During the quarter, detailed engineering and procurement advanced with the Company's contractor, with procurement package preparation and long-lead item ordering a key focus. Cleaning and environmental testing of the existing tanks, containment, and piping was completed, and demolition of existing infrastructure commenced during the quarter. The Company also progressed the tailings storage facility and new filtered tailings design work. The refurbishment timing remains on track with the engineering study timeline and scope of work. Early works and pre-construction readiness activities are well underway on site and continue to advance on schedule ahead of major construction, which is expected to commence in the fourth quarter of 2026. Second and third quarter pre-construction activities include mobilization of the EPCM contractor to site, commencement of demolition of the existing plant components requiring replacement as part of the refurbishment and advancement of detailed engineering, procurement packages, and the award of key contracts.

The Lone Tree Plant is permitted for the existing operational components in use. The approval of new and revised permit applications pertaining to air quality, mercury control, water pollution control, reclamation management, and other secondary programs for the new design remain outstanding. The Company submitted the necessary applications for air quality, mercury control and water quality environmental permits in the first quarter of 2026, as planned, with several permits received to date and further permits pending. Various construction activities are scheduled to commence in the second half of 2026 upon the anticipated approval of the associated permits, with major construction activities anticipated to commence in the fourth quarter of 2026.The permitting process is currently on track and aligns with the construction schedule.

Capital expenditures for the three months and six months ended June 30, 2026 were primarily related to the refurbishment of the Lone Tree Plant. The project spend is weighted in the second half of the year and the Company expects to meet full-year guidance.

As of June 30, 2026, total construction commitments were $110.1 million with approximately 30% of the project cost committed. Subsequent to the quarter, procurement activities remain on schedule, with approximately 50% of procurement packages, by value, awarded as of mid-July. Project capital remains on budget with minimal contingency drawdown and approximately 40% of capital committed as of mid-July.

FINANCIAL STATEMENTS

This press release should be read in conjunction with i-80 Gold's Form 10-Q, including the unaudited consolidated financial statements and associated Management's Discussion and Analysis of Financial Condition and Results of Operation for the three and six months ended June 30, 2026 included therein, which is available on the Company's website at www.i80gold.com, and under the Company's issuer profile on EDGAR at www.sec.gov and SEDAR+ at www.sedarplus.ca.

CONFERENCE CALL AND WEBCAST

Management will hold a conference call and audio webcast to discuss the second quarter highlights followed by a question-and-answer session with participants. The details are as follows:

Date:                               

Tuesday, August 11, 2026

Time:                               

10:00 a.m. ET

Webcast:                           

https://app.webinar.net/q0A61kDYpP2 

Telephone:                         

1-416-945-7677

Toll-free (North America):     

1-888-699-1199   

TECHNICAL DISCLOSURE AND QUALIFIED PERSONS

All scientific and technical information contained in this press release has been reviewed, verified and compiled under the supervision of Paul Chawrun, P.Eng., member of the Professional Engineers of Ontario (PEO) and the Company's Executive Vice President & Chief Operating Officer, and Tyler Hill, CPG., Vice President Geology for the Company, each of whom is a "Qualified Person" within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects and S-K 1300 and Subpart 1300 of Regulation S-K under the U.S. Securities Act of 1933, as amended. Mr. Chawrun and Mr. Hill have verified the scientific and technical information disclosed in this press release.

ENDNOTES

(1)

This is a Non-GAAP and Supplementary Financial measure; please see "Non-GAAP and Supplementary Financial Performance Measures" section.

(2)

Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%).

ABOUT i-80 GOLD CORP.

i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a fully funded three-phase development plan to advance its high-quality asset portfolio. The Company is one of the largest mineral resource holders in the state with a pipeline of three high-grade underground and two open pit projects strategically located in some of Nevada's most prolific gold-producing trends. Leveraging its central autoclave processing facility following an anticipated refurbishment, i-80 Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold's shares are listed on the NYSE (NYSE: IAUX) and Toronto Stock Exchange (TSX: IAU). Visit www.i80gold.com for more information.

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION

Certain information set forth in this press release, including but not limited to management's assessment of the Company's future plans and operations; the anticipated timing of the permitting, construction, refurbishment and commissioning of the Lone Tree Plant; the anticipated benefits of the refurbished Lone Tree Plant, including to cash margins, recoveries, operating margins and free cash flow generation, and the anticipated transition from toll milling to owner-operated processing; the perceived merit of projects or deposits; the impact, timing, and execution of the Company's three-phase development plan, the anticipated timing of permitting, gold output, project development, or completion dates for feasibility studies, technical studies; execution and timing of all asset advancements in the development plan; the potential to utilize the autoclave infrastructure at the Lone Tree Plant to process mineralized material pending the outcome of the refurbishment; that Mineral Point will become the Company's largest gold producing asset; the successful permitting of each project; the timing, completion and results of the Company's drill programs; the inclusion of drill results in future feasibility studies and the expected conversion of mineral resources to higher confidence categories or to mineral reserves; that any of the projects will reach commercial production; the Company's ability to achieve mid-tier producer status; outlook on gold output; the Company's 2026 production, operating, pre-development, evaluation and exploration cost guidance; the anticipated timing for water treatment plant completion at Granite Creek and the outcome of the dewatering program; the anticipated commissioning of the Lone Tree Plant by the end of 2027; the expected timing of first gold mined from Archimedes; the anticipated implementation of a hub-and-spoke regional mining and processing model; and the Company's expectation that it has sufficient liquidity to meet its obligations as they become due, constitute forward-looking statements or forward-looking information (collectively, "forward-looking statements") within the meaning of applicable Canadian and United States securities laws.

All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts", "projects", "predicts", "intends", "anticipates", "targets" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management as at the date of this press release, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Material assumptions used in preparing the forward-looking statements in this press release include, but are not limited to, assumptions regarding: the price of gold and silver; the accuracy of the Company's mineral resource estimates and the underlying geological, technical and economic parameters; anticipated costs and expenditures; the timely receipt of all required regulatory and governmental approvals and permits on acceptable terms; the availability of financing on acceptable terms; the availability of equipment, labor and contractors; the absence of significant labor disruptions or material adverse changes in general economic conditions; and the Company's ability to execute its three-phase development plan on the anticipated timeline and within budget. Readers are cautioned that the foregoing assumptions, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, undue reliance should not be placed on forward-looking statements.

The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits, if any, that the Company will derive therefrom. By their nature, forward looking statements are subject to numerous risks and uncertainties, some of which are beyond the Company's control, including: general economic and industry conditions; volatility of commodity prices, including the prices of gold and silver; title risks and uncertainties; the Company's ability to access sufficient capital from internal and external sources, including by selling assets, restructuring debt or obtaining additional equity capital, on terms that may be onerous or highly dilutive; uncertainties related to the refurbishment of the Lone Tree Plant, including cost overruns and construction delays; risks related to third-party toll milling arrangements and processing delays; uncertainties regarding water management and groundwater inflows at Granite Creek; risks related to the conversion of mineral resources and the results of feasibility and other technical studies; risks associated with mineral exploration, development and mining operations generally; risks related to obtaining and maintaining required governmental, environmental and other regulatory approvals and permits, including under NEPA and the BLM process, on a timely basis or at all; environmental, health and safety risks; risks relating to the reliance on key personnel and contractors (including Hatch); changes in applicable laws, regulations or government policies in Canada and the United States; foreign exchange and interest rate fluctuations; litigation risks; and the other risk factors discussed under the heading "Risk Factors" in the Company's Form 10-K for the fiscal year ended December 31, 2025 and the Company's Form 10-Q for the three months ended June 30, 2026, each of which is available on EDGAR at www.sec.gov/edgar and on SEDAR+ at www.sedarplus.ca. Readers are encouraged to carefully review these risk factors as well as the Company's other filings with the U.S. Securities and Exchange Commission and the Canadian Securities Administrators. All forward-looking statements contained in this press release speak only as of the date of this press release or as of the dates specified in such statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, except as required by applicable law.

Additional information relating to i-80 Gold can be found on i-80 Gold's website at www.i80gold.com, SEDAR+ at www.sedarplus.ca, and on EDGAR at www.sec.gov/edgar.

NON-GAAP AND SUPPLEMENTARY FINANCIAL PERFORMANCE MEASURES

The Company has included certain non-GAAP performance measures commonly used in the mining industry that are not defined under US GAAP in this document. These include adjusted net loss, adjusted net loss per share, and average realized price per ounce. These measures are not defined under US GAAP, and therefore, they may not be comparable to similar measures employed by other companies. Management believes these measures in addition to measures determined in accordance with US GAAP provide investors with useful information to evaluate the Company's underlying operations and financial performance. Supplementary financial measures represents a component of a GAAP number. The measures presented  are intended to provide additional information and should not be considered in isolation or as a substitute for measures prepared in accordance with US GAAP and should be read in conjunction with the Company's Financial Statements.

Definitions

"Average realized gold price" per ounce of gold sold is a supplementary financial measure and the calculation is shown below.

"Adjusted net loss"and "adjusted net  loss per share" are non-GAAP financial performance measures that the Company considers to better reflect normalized earnings because it eliminates temporary or non-recurring items such as: gain and losses on fair value measurements, loss on loan extinguishment, gain (loss) on Convertible Loans and finance fee expense. Adjusted net loss per share is calculated using the weighted average number of shares outstanding under the basic calculation of earnings per share.

"Sustaining capital expenditures" and "Growth capital expenditures" are supplementary financial measures. Sustaining capital expenditures are investments that support current operational and production levels whereas Growth capital expenditures are associated with major projects and new mine development.

Average realized gold price per ounce of gold sold(2)


Three months ended

June 30,

Six months ended

June 30,

(in thousands of U.S. dollars, unless otherwise noted)


2026

2025

2026

2025

Consolidated






Revenues


24,348

27,836

76,738

41,884

Silver revenue


(224)

(108)

(288)

(169)

Gold revenue


24,124

27,728

76,450

41,715

Gold sold¹

ounce

5,335

8,400

15,923

13,352

Average realized gold price ($/oz)

$/ounce

4,522

3,301

4,801

3,124







Granite Creek






Revenues


9,355

19,727

53,194

28,422

Gold ounces sold1

ounce

2,052

5,981

10,818

9,086

Average realized gold price ($/oz)

$/ounce

4,559

3,298

4,917

3,128







Lone Tree






Revenues


11,891

5,821

18,777

9,784

Silver revenue


(173)

(22)

(233)

(36)

Gold revenue


11,718

5,799

18,544

9,748

Gold sold

ounce

2,593

1,754

4,032

3,149

Average realized gold price ($/oz)

$/ounce

4,519

3,306

4,599

3,096







Ruby Hill






Revenues


3,102

2,288

4,767

3,678

Silver revenue


(51)

(86)

(55)

(133)

Gold revenue


3,051

2,202

4,712

3,545

Gold sold

ounce

690

665

1,073

1,117

Average realized gold price ($/oz)

$/ounce

4,422

3,311

4,391

3,174

Note to table above:
1 Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 56% in 2026 (2025 - 59%)

Adjusted net loss(2)

Adjusted net loss and adjusted net loss per share exclude a number of temporary or one-time items detailed in the following table:


Three months ended

June 30,

Six months ended

June 30,

(in thousands of U.S. dollars, unless otherwise noted)

2026

2025

2026

2025






Net loss

$      (52,527)

$      (30,215)

$    (131,128)

$      (71,420)

Adjust for:





Loss on fair value measurement of Silver Purchase Agreement derivative

(9,290)

(1,986)

(36,092)

(9,461)

Loss on fair value measurement of NSR Royalty

(24,039)

(31,663)

Finance fee expense

(9,796)

Loss on loan extinguishment

(782)

(7,110)

(782)

Gain (loss) on fair value measurement of Convertible Loans derivative

765

(3,463)

(673)

Loss on fair value measurement of Orion Gold Prepay Agreement derivative

(2,412)

(3,377)

(10,674)

Gain / (loss) on Offtake liability

(4,800)

(4,800)

Gain on fair value measurement of 2026 Gold Prepay derivative

22,000

29,893

Gain on fair value measurement of warrant liabilities

4,766

709

5,169

275

Total adjustments

$      (11,363)

$       (3,706)

$      (61,239)

$      (21,315)

Adjusted net loss

(41,164)

(26,509)

(69,889)

(50,105)






Weighted average shares

861,071,221

608,167,841

849,153,360

520,243,077

Adjusted net loss per share

$        (0.05)

$        (0.04)

$        (0.08)

$        (0.10)

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/i-80-gold-reports-second-quarter-2026-results-on-track-to-achieve-full-year-guidance-as-granite-creek-ramps-up-and-development-plan-advances-302847553.html

SOURCE i-80 Gold Corp